A tenant improvement (TI) allowance is the landlord’s contribution toward building out your space — usually negotiated as a dollar amount per square foot and spelled out in the lease’s work letter. Tenants routinely plan around that number as if it were the budget for the whole job. It isn’t. The allowance covers a defined slice of the build, everything outside that slice is yours, and the gap is where fit-out budgets get surprised.
What a TI allowance typically covers
The allowance is meant for permanent improvements — the construction that stays with the space when you eventually leave. In most commercial leases that means the hard construction costs of the build-out itself:
- Framing, drywall, ceilings, and interior doors and hardware
- Flooring, paint, and other base finishes
- Lighting and electrical distribution inside the space
- HVAC distribution — ductwork and diffusers running from the building’s existing system
- Plumbing for restrooms, break rooms, and similar built-in needs
- Sprinkler coverage and other life-safety work the code requires
The common thread: if it’s part of the space itself, it’s usually allowance-eligible — subject to the exact language in your work letter.
What it typically doesn’t cover
- Furniture, fixtures, and equipment. Desks, seating, shelving, and the equipment your business runs on are yours, not the landlord’s.
- Your technology. Structured cabling, security, AV, and IT systems are usually tenant costs, even though they go in during the build.
- Signage. Interior and exterior signs are commonly excluded or handled under a separate, smaller provision.
- Design and professional fees. Architect and engineer fees are covered in some deals and excluded in others — this is one of the first items to confirm, because it’s spent before construction even starts.
- Moving and downtime. Relocation, temporary space, and lost business during construction are never part of the allowance.
- Anything over the allowance. Every dollar the build runs past the TI amount comes out of your pocket, at exactly the point in the job when changing course is most expensive.
The mechanics matter as much as the amount
An allowance isn’t a check handed over at lease signing. It’s typically disbursed as the work progresses or after completion, against invoices, lien waivers, and inspections — which means you may be carrying the cash during construction even for covered items. Plans usually need the landlord’s approval before work starts, work done outside the approved plans may not qualify, and most allowances come with a use-it-by deadline: funds not claimed in time are commonly forfeited. Read the work letter before you price the job, not after.
How to size the build to the allowance
Price the real scope first, then compare it to the allowance — not the other way around. A fit-out designed to a guessed number produces change orders; a fit-out priced from your actual space tells you, before you sign, whether the allowance covers the build or how much of your own capital to plan on top of it. That early budgeting and feasibility work is what C2 Construction Group does in pre-construction, so the negotiation with your landlord is built on a real number.